UPDATE: Underhill Playground upgrades "Real Soon Now"

Underhill_playground_sign_1Joan says she spoke to Marty Maher, who is in charge of capital projects for Brooklyn parks: "He told me that it has been bid out a 3rd time – the first, bids came in way too high; the second time they were out of order; and now it’s been bid out again. They have to wait 60 days for bids to come in, and then approximately another 30 days to award it.  Based on that timeline, construction will start late spring or early summer. It won’t be postponed anymore, given how long it’s taken this project to get off the ground."
COMING SOON (hopefully): a design schematic for the proposed upgrades.

Notice: This work is licensed under a BY-NC-SA. Permalink: UPDATE: Underhill Playground upgrades "Real Soon Now"